Ozan Creeks Watershed
A work plan for watershed protection and flood prevention in the Ozan Creeks
Watershed was finalized in 1975. Since that time, 8 of 22 planned floodwater
retarding structures and about 250 acres of land stabilization measures have
been completed.
Ozan Creek Site 13
Site 13 is under construction north of Hope. The site will have a 15-acre
reservoir with a 205-acre drainage area. The design features the reservoir with
a 32-foot dam, a 2-foot principal spillway pipe and a 50-foot wide emergency
spillway providing 114 acre-feet of floodwater storage.
Ozan Creek Site 12
Site 12, about a mile from Site 13, has a 29-foot dam with a 20.3 acre
reservoir with a 475-acre drainage area.